prim80457:Duration Distributions multiplied by 8 when importing MSP Schedule.
Solution ID: prim80457
Duration Distributions multiplied by 8 when importing MSP Schedule.
Status: Reviewed
Version(s): 8.5
Problem:
Duration distributions multiplied by 8 when importing MSP schedule.
Problem:
When importing duration distributions for a Microsoft Project plan and choosing hours as the planning unit, the duration distributions are multiplied by 8.
Problem:
Duration distributions incorrect when importing an MSP schedule.
Fix:
This known problem in Pertmaster 8.5.0030 has
| Solution ID: prim80457 |
| Duration Distributions multiplied by 8 when importing MSP Schedule. |
| Status: Reviewed |
| Version(s): 8.5 |
| Problem: | Duration distributions multiplied by 8 when importing MSP schedule. |
| Problem: | When importing duration distributions for a Microsoft Project plan and choosing hours as the planning unit, the duration distributions are multiplied by 8. |
| Problem: | Duration distributions incorrect when importing an MSP schedule. |
| Fix: | This known problem in Pertmaster 8.5.0030 has been corrected in Primavera Risk Analysis 8.6.0017. To download the latest version of the software, please click here. |
| Fix: | Workaround: Create calculated value columns dividing the MIN/ML/MAX by 8. Then copy and paste those values into the actual MIN/ML/MAX columns. |
Related Posts
- prim57699:In P6 what’s the difference between the ‘Team Member’ and ‘Timesheet’ license?
- prim80403:WBS codes not numbered correctly after importing from MS Project
- prim80319:How to have additional custom fields imported to Evolve from MS Project via ProjectLink
- prim80259:How to export Impacted Risk Data to Microsoft Project.
- prim84363:"Error: "The process completed with errors"; NULL values in Microsoft Project file





Leave a Reply