prim80457:Duration Distributions multiplied by 8 when importing MSP Schedule.

prim80457:Duration Distributions multiplied by 8 when importing MSP Schedule.

Solution ID: prim80457

Duration Distributions multiplied by 8 when importing MSP Schedule.

Status: Reviewed

Version(s): 8.5

Problem:
Duration distributions multiplied by 8 when importing MSP schedule.

Problem:

When importing duration distributions for a Microsoft Project plan and choosing hours as the planning unit, the duration distributions are multiplied by 8.

Problem:
Duration distributions incorrect when importing an MSP schedule.

Fix:
This known problem in Pertmaster 8.5.0030 has

Solution ID: prim80457
Duration Distributions multiplied by 8 when importing MSP Schedule.
Status: Reviewed
Version(s): 8.5
Problem: Duration distributions multiplied by 8 when importing MSP schedule.
Problem:

When importing duration distributions for a Microsoft Project plan and choosing hours as the planning unit, the duration distributions are multiplied by 8.

Problem: Duration distributions incorrect when importing an MSP schedule.
Fix: This known problem in Pertmaster 8.5.0030 has been corrected in Primavera Risk Analysis 8.6.0017.  To download the latest version of the software, please click here.
Fix: Workaround:

Create calculated value columns dividing the MIN/ML/MAX by 8.  Then copy and paste those values into the actual MIN/ML/MAX columns.

Related Posts

Did you enjoy this post?

If so, would you please consider sharing it with the world

Leave a Reply

Default User

Your Name

March 09, 2010

You must be logged in to post a comment.